About Us Key Dates
      
     
  • Request for Proposals Issued
10 June 2000
  • Development Proposal Submission
25 March 2001
  • Final Proposal Clarifications
2 June 2001
  • Effective Date of PWPA
31 July 2001
  • Limited Notice to Proceed to EPC Contractor
1 August 2001
  • Signing of EPC Contract
24 November 2001
  • Signing of O&M Agreement
28 November 2001
  • Financial Closing Date
7 December 2001
  • Notice to Proceed Issued to EPC Contractor
7 December 2001
  • Site Preparation Completed
31 July 2002
  • Mechanical Completion Date
1 April 2004
  • Completion of Special Facilities
15 April 2004
  • Fist Power Unit COD
16 May 2004
  • First Desalination Unit COD
16 June 2004
  • Scheduled Project Commercial Operation Date
17 August 2004
 