About Us
Key Dates
Request for Proposals Issued
10 June 2000
Development Proposal Submission
25 March 2001
Final Proposal Clarifications
2 June 2001
Effective Date of PWPA
31 July 2001
Limited Notice to Proceed to EPC Contractor
1 August 2001
Signing of EPC Contract
24 November 2001
Signing of O&M Agreement
28 November 2001
Financial Closing Date
7 December 2001
Notice to Proceed Issued to EPC Contractor
7 December 2001
Site Preparation Completed
31 July 2002
Mechanical Completion Date
1 April 2004
Completion of Special Facilities
15 April 2004
Fist Power Unit COD
16 May 2004
First Desalination Unit COD
16 June 2004
Scheduled Project Commercial Operation Date
17 August 2004