Key event |
Key Date |
- Request for Proposals Issued
|
April 2002 |
- Development Proposal Submission
|
18 November 2002 |
- Effective Date of UAN PWPA
|
12 March 2003 |
|
30 June 2003 |
|
2 July 2003 |
- Notice to Proceed to EPC Contractor
|
11 July 2003 |
|
16 July 2003 |
- Scheduled Completion of Gas Turbines 1-3
|
22 June 2005 |
- Scheduled Integration of UAN West B Assets
|
22 July 2005 |
- Scheduled Project Commercial Operation Date
|
22 June 2006 |
- Assumed Commercial Operation End Date for Old Existing Assets
|
6 July 2008 |
- True Up Drawing Date/Equity Subscription Date
|
21 July 2008 |