About Us Key Dates
      
     
  Key event
Key Date
  • Request for Proposals Issued
April 2002
  • Development Proposal Submission
18 November 2002
  • Effective Date of UAN PWPA
12 March 2003
  • UAN PWPA Closing Date
30 June 2003
  • Signing Date
2 July 2003
  • Notice to Proceed to EPC Contractor
11 July 2003
  • Financial Closing Date
16 July 2003
  • Scheduled Completion of Gas Turbines 1-3
22 June 2005
  • Scheduled Integration of UAN West B Assets
22 July 2005
  • Scheduled Project Commercial Operation Date
22 June 2006
  • Assumed Commercial Operation End Date for Old Existing Assets
6 July 2008
  • True Up Drawing Date/Equity Subscription Date
21 July 2008
 